When I set a start date for an activity, it sets the end date automatically. Is there a way to disable that so I can set the duration of tasks individually?
Date
Votes
1 comment
-
AEC Software Support Rep Official comment If a start date is entered and duration of the activity has not been set, then FastTrack Schedule always assumes a 1 day activity. Consider entering the duration first then entering the Start Date.