When I open the assignments row for resources in the Resource View, the tasks are not in the same order that I entered in the Schedule View. Is there any way to get the same order for tasks under the Resource View as that in the Schedule View?
When I open the assignments row for resources in the Resource View, the tasks are not in the same order that I entered in the Schedule View. Is there any way to get the same order for tasks under the Resource View as that in the Schedule View?
Hello John,
Activities within the Resource Sub Row "Assignments" will appear in the order in which the resource was assigned to the, so the only direct way to show them in the same order of the Schedule View would be to assign a resource in the schedule from top to bottom. If a resource was assigned, later unassigned from the activity and eventually reassigned it would move the activity in the Resource View below the activity the resource was previously assigned to.
We cannot currently re-order the information because it is not stored within its own unique column in FastTrack. We do have this on our list for a feature update in a future version of FastTrack, so I'll be sure to pass on that we have other users asking for this ability.