Is there any way to calculate durations between tasks or the entire project with the inclusion of lead/lag times?

I could use another calculator to do a date calculation between project start and finish, but did not know if FTS handled this.  In other words, total project duration is a sum of work/effort in all tasks, but stays constant even when lead/lags are included.  For some projects, you need to "finish in 120 calendar days" which is not the same as total effort.