Knowledge Base & Forums/Community Forum/Community Questions & Answers

Answered

Allocating resource hours to tasks.

Jane
asked this on June 15, 2011 17:59

Is there a way that I can allocate a resource to a task and lock the number of hours that the resource has been allocated so that if the timeline for the task is stretched the hours are re-distributed across the task? At the moment, when I stretch the schedule bar to increase the timeline work units are added rather than stretched out over the course of the task.

 

Thanks